Las Cruces, Guatemala

The Community

Village of over 18,000 people located in a largely deforested former jungle region subject to serious flooding. Engineers Without Borders worked in partnership with the local community, municipal government, and the in-country NGO Concern America to address flooding risks. Concern America supported coordination with local stakeholders and helped facilitate long-term, community-driven engagement throughout the project.

The Need

The Las Cruces Drainage Commission requested assistance to better understand the causes of flooding and to develop effective flood mitigation strategies. The community needed technical analysis to evaluate stormwater behavior and to design practical solutions to reduce the severity and extent of flooding throughout the town.

our Involvement

  • 2009 – Initial Assessment Trip
    • Established relationships with community, government officials and local NGO
    • Performed community health, water quality and topographical surveys
  • 2010 – Submitted preliminary project report to EWB-USA, NGO and community
    • Completed preliminary hydraulic analysis and cost estimates to evaluate alternative flood reduction mechanisms
  • 2011 – Assessment Trip
    • Detailed hydrologic and hydraulic analysis of existing stormwater conditions 
    • Evaluation of improvements to reduce the severity and extent of flooding problems. 
    • The preferred alternative was the construction of a 4.5 km channel to intercept flows and route them around the town.
  • 2012 – Submitted flood mitigation plans
    • Flood mitigation plans, specifications and estimates were delivered to a government agency, Segeplan who provided the plans and reports to the new Las Cruces municipal government
    • The government retained a Guatemalan consultant to prepare the final plan which included elements of the EWB-CPC plan but also had significant changes
  • 2013 – First construction phase initiated by Guatemalan consultant
    • Followed up with Segeplan and the project began its first construction phase in late 2013
    • Two team members acquired data for a clean, reliable water source for the recently relocated community health clinic
  • 2014 – Monitoring Trip
    • Assessed the completed well which was drilled at health clinic by local contractor according to EWB-CPC design and its water quality was good
    • Helped the clinic workers develop a plan to clean and disinfect rainwater storage tank
    • Found that the storm water diversion channel was being constructed although the routing and capacity had been changed from the original EWB plan
Following the June trip, the team determined that the program was successfully in the hands of local organizations and the program was closed out with EWB-USA

THE RESULTS

Through multiple assessment, analysis, and monitoring trips between 2009 and 2014, Engineers Without Borders–Chicagoland Professional Chapter completed detailed hydrologic and hydraulic studies and developed flood mitigation plans for the community. A preferred solution involving the construction of a 4.5 km stormwater diversion channel was identified to intercept and route floodwaters around the town.
Flood mitigation plans, specifications, and cost estimates were delivered to the Guatemalan government agency Segeplan and subsequently shared with the Las Cruces municipal government. While a Guatemalan consultant later modified the final design, construction of the stormwater diversion system began in late 2013. Additional outcomes included the successful design and installation of a clean water well at the community health clinic, confirmation of good water quality, and support for rainwater storage disinfection planning. By 2014, the project had transitioned fully to local organizations, and the program was formally closed out with EWB-USA.